Walmart

Problem

In 2017 Rogers was approached by Walmart to tackle the Fresh Angle Project. Rogers technicians met with Walmart’s reset team to relocate power to each of the berry, bakery and floral cases. Rogers did the original install of power for each of these coolers back in 2016 and was tasked to relocate them for a new layout within the Fresh Angle Project. Rogers was given a scope to demo existing power drops to each of the cases and cap off power, install a cut in box and outlet on each well and tap off and finish with covering up each of the newly installed outlets once plugged in.

Solution

Rogers facilitated crews to 2600+ locations nationally over a 4 month timeline. This project was completed with 1 electrician/1 night. Rogers’ project management teams allowed Walmart real-time updates with access to on-site pictures, work order notes, as well as a dedicated account manager throughout the duration of the project.